Physically Monitored Schemes/ Projects under different Department
during 2022- 23
Statement Showing the Projects/Schemes under different Department to be
Physically Monitored by the Officers of Evaluation & Monitoring Division:
NAGAON DISTRICT – December 2022
SL.NO |
NAME OF THE PROJECTS/SCHEMES |
NAME OF EXECUTING COMMITTEE/ DEPARTMENT |
VISITING OFFICER |
SANCTIONED AMOUNT |
RELEASE AMOUNT |
PHYSICAL PROGRESS |
FINANCIAL PROGRESS |
REMARKS |
1 |
A construction of auditorium at Nagaon Bengali Association, Nagaon sadar LAC under UNTIED FUND SCHEME |
Construction Committee headed by ADC, Nagaon |
Bhuban Ch. Deka, COD, E&M Division Raja Basfor, RA, E&M Division |
50 Lakh |
29.50 Lakh |
50% |
60% |
Work Under Progress |
2 |
A construction of Model Anganwadi Centre at Ujjan Haibargaon LPS, Nagaon Sadar LAC under ICDS SCHEME |
District Level Monitoring Committee headed by District Social Welfare Officer, Nagaon |
-do- |
25 Lakh |
24.25 Lakh |
100% |
100% |
Work Completed |
3 |
A construction of Model Anganwadi Centre at Sibasthan LPS, Nagaon Sadar LAC under ICDS SCHEME |
-do- |
-do- |
-do- |
-do- |
-do- |
-do- |
-do- |
4 |
A construction of New Building at Borkola HS School, Nagaon Sadar LAC under MsDP SCHEME |
PWD (Building) Division |
-do-
|
175 Lakh |
87.50 Lakh |
90% |
50% |
Work Under Progress |
5 |
A construction of Girls Hostel (100 Beded) at Borkola HS School, Nagaon Sadar LAC under MsDP SCHEME |
PWD (Building) Division
|
-do-
|
158 Lakh |
79 Lakh |
90% |
50% |
Work Under Progress |
6 |
A construction of roof truss in second floor of Bhogeshwari Hazarika Girls Higher Secondary School, Nagaon Sadar LAC under UNTIED FUND SCHEME |
Construction committee headed by School Principal |
-do-
|
5 Lakh |
2.95 Lakh |
80% |
60% |
Work Under Progress |
7 |
A Construction of Teacher Common Room at Raha HS School, 82 Raha LAC under UNTIED FUND SCHEME |
Construction Committee headed by CEO, Zilla Parishad CEO |
-do- |
30 lakh |
25.20 |
95% |
95% |
Work Under Progress |
SIVSAGAR DISTRICT- December 2022
SL.NO |
NAME OF THE PROJECTS/SCHEMES |
NAME OF EXECUTING COMMITTEE/ DEPARTMENT |
VISITING OFFICER |
SANCTIONED AMOUNT |
RELEASE AMOUNT/ EXPENDITURE |
PHYSICAL PROGRESS |
FINANCIAL PROGRESS |
REMARKS |
1 |
Improvement of road from Tetelitol tiniali to Hologuri tiniali under RIDF- XXVII for the year 2021-22 in PWDR, Sivsagar & Thowra territorial road division, Sivsagar, Thowra LAC, Length = 9.30km |
PWDR Sivsagar & Thowra territorial road division, Sivsagar, Thowra LAC |
Pranita Devi Mahanta, ARO, E&M Division Barsha Rani Das, RA, E&M Division Bornali Bora, RA, E&M Division |
10 Cr |
7.35 Cr |
75.45% |
73.57% |
Work Under Progress |
2 |
Mustard area expansion and technology demonstration at Bahir Ligiribari, Desangmukh, Sivsagar LAC, Under RKVY |
Department of Agriculture, under ADO Kanworpur Circle, Sivsagar |
-do- |
|
|
100% |
100% |
Work Completed |
3 |
Construction of Sivsagar Natya Mandir at Sivsagar Town, Sivsagar LAC under UNTIED FUND |
Construction committee headed by PWD (Building) Division, Sivsagar |
-do- |
195.60 Lakh |
156.78 Lakh |
60 % |
60% |
Work Under Progress |
4 |
Construction of commercial complex at Amguri Municipal Board, Amguri LAC under 15th FINANCE COMMISSION |
Amguri Municipal Board headed by Asstt. Engineer, Amguri |
-do- |
34.26 Lakh |
21.99 Lakh |
65% |
65% |
-do- |
5 |
Construction of Sports complex at Amguri, Amguri LAC, SIGNATURE PROJECT |
PWD (Building) Division headed by Executive Engineer, Sivsagar |
-do- |
10 Cr |
8.9 Cr |
98% |
89% |
-do- |
6 |
Buddhist destination centre at Sivsagar, Sivsagar LAC under ATDC |
Tourism Deptt. Through NEC headed by AEE ATDCL |
-do- |
340 Lakh |
330 Lakh |
98% |
97% |
-do- |
7 |
Preservation of Bakhor Begena Tree at Jobolating Village, Thowra LAC under UNTIED FUND |
PWD (Building) Division, Sivsagar headed by Executive Engineer |
-do- |
50 Lakh |
Nil |
0% |
0% |
-do- |
8 |
RAICHAI WSS at sukanpukhuri, Thowra LAC under JJM |
Empanelled Contractor, PHED, Sivsagar |
-do- |
283.54 Lakh |
Nil |
0% |
0% |
-do- |
9 |
Construction kaliapani Grant No. WSS at demow, Thowra LAC under JJM |
-do- |
-do- |
288.61 Lakh |
149.297 Lakh |
80% |
54% |
-do- |
10 |
Construction of raichai rural stadium at Demow, Thowra LAC under signature project |
PWD Division headed by Executive Engineer, Sivsagar |
-do- |
12.66 Cr |
Nil |
10% |
0% |
-do- |
11 |
Bornoi land reclamation project (excavation of the congested part), under Nazira LAC |
Soil conservation department under SOPD- G, jorhat soil conservation division |
-do- |
25 lakh |
Nil |
50% |
0% |
-do- |
12 |
Improvement of i) dhodar ali road (from ch. 110.80 km to ch. 122.70km) ii) Mezenga station Feeder Road from ( Ch. 0.00km to 11.20 km) iii) Bortol Gelekey Road ( From ch. 8.20 km to ch. 14.44 km) under SOPD (G) for the year 2019-20 under PWRD, Nazira & Amguri Territorial Road Division, Nazira |
PWRD, Nazira & Amguri Territorial Road Division, Nazira headed by AE |
-do- |
36.22 Cr |
34.13 Cr |
99% |
94% |
-do- |
13 |
SIMRA LINE PWSS, Nazira LAC under JJM |
PHED, Nazira/ Sivsagar division, headed by JE |
-do- |
87 Lakh |
Nil |
>50% |
Nil |
-do- |